Quantitative Aptitude For IBPS PO/Clerk Prelims: 7th February 2019

February 7, 2019    

Dear Aspirants,



Quantitative Aptitude Quiz For IBPS PO/Clerk Prelims

Numerical Ability or Quantitative Aptitude Section has given heebie-jeebies to the aspirants when they appear for a banking examination. As the level of every other section is only getting complex and convoluted, there is no doubt that this section, too, makes your blood run cold. The questions asked in this section are calculative and very time-consuming. But once dealt with proper strategy, speed, and accuracy, this section can get you the maximum marks in the examination. Following is the Quantitative Aptitude quiz to help you practice with the best of latest pattern questions.




Q1. A and B can do a piece of work in 72 days. B and C can do it in 120 days. A and C can do it in 90 days. In what time all of them can do it together?
80 days
100 days
120 days
150 days
60 days
Solution:

Q2. A is thrice as good a workman as B and therefore is able to finish a job in 30 days less than B. How many days will they take to finish the job working together?
Solution:

Q3. 9 men working 7 hours a day can complete a piece of work in 15 days. In how many days can 6 men working for 9 hours a day, complete the same piece of work ?
63/4 days
16 days
67/4 days
35/2 days
None of these
Solution:
Let required days are x
Then
9 × 7 × 15 = 6 × 9 × x
⇒ x = 35/2 days.

Q4. Bharat and Priyanka can do a piece of work in 45 and 40 days respectively. They began the work together, but Bharat leaves after some days and Priyanka finished the remaining work in 23 days. After how many days did Bharat leave?
7 days
8 days
9 days
11 days
None of these
Solution:

Q5. Ramesh is twice as good a workman as Sunil and Finishes a piece of work in 3 hours less than Sunil. In how many hours they together could finish that piece of work?
Solution:

Q6. A and B can do a piece of work in 9 days and 18 days, respectively. As they were ill, they could do 90% and 72% of their efficiency, respectively. How many days will they take to complete the work together?
   8
   5
   10
   None of these
Solution:

Q7. B is twice efficient as A and A can do a piece of work in 15 days. A started the work and after a few days B joined him. They completed the work in 11 days, from the starting. For how many days did they work together?
1 day
2 day
6 days
5 days
None of these
Solution:

Q8. A can do some work in 24 days, B can do it in 32 days and C can do it in 60 days. They start working together. A left after 6 days and B left after working for 8 days from start. How many more days are required to complete the whole work?
30
25
22
20
None of these
Solution:

Q9. P can cultivate 2/5th of the land in 6 days, Q can cultivate 1/3rd of the same land in 10 days, working together P and Q can cultivate 4/5th of the land in:
Solution:

Q10. A is 60 % more efficient than B. In how many days will A and B working together complete a piece of work which A alone takes 15 days to finish?
Solution:

Q11. A and B can do a piece of work in 28 and 35 days respectively. They both began to work together but A leaves after sometimes and B completed remaining work in 17 days. After how many days did A leave?
Solution:

Q12. Ajit can do as much work in 2 days as Baljit can do in 3 days and Baljit can do as much in 4 days as Diljit in 5 days. A piece of work takes 20 days if all work together. How long Baljit take to do all the work by himself ?
82 days
44 days
66 days
50 days
62 days
Solution:

Q13. 25 men and 15 women can complete a piece of work in 12 days. All of them start working together and after working for 8 days the women stopped working. 25 men completed the remaining work in 6 days. How many days will it take for completing the entire job if only 15 women are put on the job?
27 days
88 days
32 days
46 days
36 days
Solution:

Q14. A man can type 20 lines in 10 minutes but he leaves 8% margin in each line. In how much time will he type 23 pages with 40 lines on each page leaving 25% more margin than before?
6hr 30min
7hr 45min
6hr 45min
7hr 30min
8hr 45 min
Solution:

Q15. A can do 50% more work than B can do in the same time. B alone can do a piece of work in 20 hr. A, with the help of B, can finish the same work in how many hours?
Solution:

               



          
          
Check the Video Course of Quantitative Aptitude  


Print Friendly and PDF

Let's block ads! (Why?)

Quantitative Aptitude For IBPS PO/Clerk Prelims: 7th February 2019 4.5 5 Yateendra sahu February 7, 2019 Dear Aspirants, Quantitative Aptitude Quiz For  IBPS PO/Clerk Prelims Numerical Ability or Quantitative Aptitud...


Related Post:

Load comments

No comments:

Post a Comment