1. Mohan and Sohan can do a job in 12 days. Sohan alone can finish it in 28 days. In how many days can Mohan alone finish the work?
(1) 25 days
(2) 21 days
(3) 18 days
(4) 15 days

2.Mary and Maurice can do a piece of work in 10 days and 15 days respectively. They work together for 3 days and then Maurice leaves. Mary finishes the remaining work alone. In how many days is the total work finished?
(1) 5 days
(2) 2 days
(3) 8 days
(4) 10 days
3.A and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days. How long would each take separately to do the same work?
(1) A-30 days,B-20 days,C-60 days
(2) A-20 days,B-30 days,C-60 days
(3) A-60 days,B-20 days,C-30 days
(4) A-20 days,B-60 days,C-30 days
4.Keberi takes twice as much time as Kanti and thrice as much as kalpana to finish a piece of work. They together finish the work in one day. Find the time taken by each of them to finish the work.
(1) Kaberi = 6 days,Kanti = 4 days, kalpana = 2 days
(2) Kaberi = 4 days,Kanti = 3 days, kalpana = 6 days
(3) Kaberi = 4 days,Kanti = 6 days, kalpana = 3 days
(4) Kaberi = 6 days,Kanti = 3 days, kalpana = 2 days
5.A, B and C can do a work in 10, 12 and 15 days, respectively. If B leaves after 2 days, how long would it take A and C to complete the remaining work?
(1) 3 days
(2) 6 days
(3) 1 days
(4) 5 days
6.P can do a work in 12 days. Q works 60% more fast then P, then in how many days Q alone would finish the work?
(1) 7 (3/2)days
(2) 8 (1/2)days
(3) 6 days
(4) 7 (1/2) days
7. Suresh can do 3/4 th part of a work in 15 days and Mohan completes the rest part of work in 3 days, in how many days Suresh and Mohan together can finish the work
(1) 25/5 days
(2) 21/2 days
(3) 18 days
(4) 15/2 days
8.Ramesh is thrice as good as workman as Bipan, and is therefore able to finish a piece of work in 40 days less than Bipan, find the time for both together to complete the work
(1) 12 days
(2) 15 days
(3) 18 days
(4) 13 days
9.If 3 men or 4 women can complete a job in 43 days then in how many days 7 men and 5 women can complete the some job?
(1) 12 days
(2) 11 days
(3) 14 days
(4) 10 days
10.If 5 men and 2 Women working together can make bricks four times more than a man and a woman working together. Compare the work of a man with that of a woman.
(1) 2/1  
(2) 1/2 
(3) 2/3
(4) 3/2

Note : Answers will be updated soon................






Quant Quiz For SSC and FCI 2015 On Time and Work 4.5 5 Yateendra sahu September 28, 2015 1. Mohan and Sohan can do a job in 12 days. Sohan alone can finish it in 28 days. In how many days can Mohan alone finish the work? (1) 25...


Related Post:

  • SA ARMOURY - 14th February
    Dear Students, At SSC Adda, we're making all the possible efforts to make your Studies fun and Interactive. Every Day we provide you all the posts combined into a single post to help you locate all the information published on a particular da… Read More
  • Must Know concepts of Tense
    Dear Readers, This video focuses on the MUST KNOW THE CONCEPTS OF TENSE FOR( SBI PO and SYNDICATE BANK). It is very useful for upcoming exams like SBIPO, SSC CGL, SBI PO 2017, BANK PO, RAILWAYS, SBI PO VACANCY, IBPS, CLERK and other competitive exams… Read More
  • Few Hours Left of Flat 14% Off on all Career Power Test Series
    Celebrate Valentine’s Day in a different way…Fall in Love with your Career and Studies. Few Hours Left...Make the most out of this opportunity This Valentine’s Day Adda247 along with its units Bankersadda, SSCadda and Career Power bring Fl… Read More
  • Alphabetical series for SSC CGL Exam
    Directions (1-3): In each of the following letter series, some of the letters are missing which are given in that order as one of the alternatives below it. Choose the correct alternative. Q1. a b _ b b c _ c _ a b _ a b _ b (a) ccaac (b) cbabc (… Read More
  • Questions on Polity for SSC CGL 2017
    Read More
Load comments

No comments:

Post a Comment