Chapterwise Quant Quiz For SSC CGL 2016 : TOPIC-TIME AND WORK (PART-II)

May 16, 2016    

Dear Readers,

As SSC CGL exam is coming near, many of candidates are studying very hard for this exam and want to crack this exam very seriously. Many of candidates understand this thing that QUANTITATIVE APTITUDE Section plays a pivotal role in deciding the cut-off for candidates giving this exam.

Friends, from now on We are starting an online quiz series of "Arithmetic Quant". According to this plan, we would be publishing daily quiz of Arithmetic maths portion from where we would cover a topic each in it and we would update it daily. 
AND ALSO THIS QUIZ SERIES IS NOT PARTICULARLY FOR SSC EXAM BUT ALSO USEFUL FOR OTHER GOVERNMENT EXAM.


1.‘Ashok’ can do a piece of work in x days and Bagish can do the same work 3x days. To finish the work together they take 12 days. What is the value of x? 
(a) 8
(b) 10
(c) 12
(d) 16

2.Arun, Bakhem and Chintoo can complete a work in 2 h. If Arun does the job alone in 6 h and Bakhem in 5 h, how long will it take for Chintoo to finish the job alone? 


3.X and Y together can complete a work in 3 days. They started together but after 2 days, Y left the work. If the work is completed after 2 more days, Y alone could do the work in how many days? 
(a) 5
(b) 6
(c) 7
(d) 10

4.40 worker can build a wall 200 m long in 12 days, working 8 h a day. What will be the number of days that 30 worker will take to build a similar wall 300 m long, working 6 h per day?
(a) 32
(b) 18
(c) 36
(d) 9

5.90 men are engaged to do a piece of work in 40 days but it is found that in 25 days, 2/3 work is completed. How many men should be allowed to go off, so that the work may be finished in time? 
(a) 10
(b) 15
(c) 20
(d) 25 



7.Aamir takes twice as much time as Shiva and Makku takes thrice as much time as Shiava to finish a work. Working together, they can finish the work in 12 days. Find the number of days needed for Aamir to do the work alone. 
(a) 20
(b) 22
(c) 33
(d) 44



9.A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work, How many men can be discharged now, so that the work may finish in time? 
(a) 40
(b) 50
(c) 48
(d) 56


10.P and Q each working alone can do a work in 15 days and 25 days, respectively. They started the work together but Q left after some time and P finished the remaining work in 7 days. After how many days from the start did Q leave? 
(a) 3
(b) 5
(c) 7
(d) 9

Answers will be updated soon..